:2024-12-30 15:27:12:
When testing current transformers, the following aspects should be noted:
1. Security measures
① Compliance with safety regulations: On site experiments should adhere to electrical safety operating procedures and take appropriate safety measures. The primary and secondary terminals of the test transformer should be independent of the circuit, disconnected from other circuits, and have obvious disconnection points. Prevent the voltage of the transformer from rising back to other circuits. Before the test, it is necessary to conduct an electrical check and install a grounding wire before proceeding with the experimental work.
② Personal protection: Staff should wear insulated gloves and boots to avoid electric shock accidents. Avoid contact with high-voltage equipment to reduce the risk of electric shock.
2. Equipment inspection and preparation
① Transformer inspection: Check the appearance of the transformer to ensure that there is no damage or defect. Use a multimeter to test the insulation resistance of the transformer to ensure safety and reliability. In addition, the connection lines and grounding of the transformer should be checked to ensure its normal operation.
② Preparation of testing equipment: Ensure that the testing equipment used (such as ammeters, voltmeters, etc.) is accurate and reliable. The accuracy and precision of the device can be checked by comparing it with standard equipment.
3. Test steps and operations
① Disconnect the power supply: First, disconnect the relays of the power supply and transformer to ensure the safety of the operation.
② Correct connection: Connect the testing device correctly to the input and output terminals of the transformer.
③ Operating standards:
a、 Select the operating current of the calibrator based on the secondary current of the tested transformer.
b、 The mechanical calibrator needs to select the magnification gear according to the size of the tested transformer level, while the fully automatic transformer calibrator will automatically select the gear according to the tested transformer level.
c、 Before operation, it is necessary to check the gear of the calibrator and select the current gear.
d、 If the polarity indicator of the calibrator is found to be activated during the experiment, the voltage regulator should be immediately lowered to zero, and then the power supply should be disconnected for inspection.
Kvtester Electronics Technology Co.,Ltd. is a high-tech enterprise specializing in power testing, testing, research and development, production, and sales of testing equipment. It has been engaged in the electrical testing industry for many years, and its products are of high quality. We welcome customers to come and purchase. Service hotline: 0086-27-81778799, to learn more, visit the official website: www.kvtester.com